Daily Progress Report
Field Work Summary - July 01, 2025
Project: Smith Beach House ~ Rough-in
Site: 123 Main Lane, Anna Maria, FL
Builder: Better Built
Super: Jason Smith | (941) 495-4600
Homeowner: Jack & Jill Smith
Report Date: July 01, 2025
6
Tasks Completed
2
Tasks In Progress
34
Tasks Remaining

Completed Tasks (6)

Tasks In Progress (2)

Remaining Tasks (34)

📦 Materials & Products Still Needed

Materials Required

  • Cat6 Cable Blue: 4 runs (TV Outlets remaining)
  • Cat6 Cable Grey: 6 runs (WiFi Access Points)
  • Cat6 Cable White: 8 runs (Surveillance Cameras)
  • Cat6 Cable Green: 2 runs (Touchscreen/Doorbell)
  • Cat6 Cable Black: 1 run (Demarc completion)
  • Mudrings: 28 units (various locations)
  • 16/4 Speaker Cable: 8 runs (Audio speakers)
  • 18/4 Cresnet Cable: 25 runs (Lighting keypads)
  • 18/2 Cable: 2 runs (Security)
  • 4x4 Junction Box: 1 unit (Demarc)

Products Required

  • Klipsch DS-180 Brackets: 8 units (4 pairs speakers)
  • Touchscreen Back Box: 1 unit (C4 Touchscreen)
  • C4-DIN-5PAN Panels: 2 units (Lighting control)
  • C4-DIN-TB-8REL: 2 units (Lighting control)
  • C4-DIN-8DIM: 7 units (Lighting control)
  • Lutron QSPS-10PNL Panel: 1 unit (Motorized shades)

📋 Procurement Notes

Priority Items: 4x4 Junction Box needed to complete Demarc work in progress

Next Phase: All lighting control products should arrive before keypad installation begins

Delivery Coordination: Speaker brackets needed before audio rough-in can start